Posey County WESTERN Bypass
PRELIMINARY SCHEDULE
FOR PHASE 1
Roadway Design: Ongoing; Complete Summer 2023
Geotechnical Investigation: Begin Early 2022
Land Acquisition: Begin Fall 2022
Construction: Begin Early 2024
Anticipated Construction Duration: 18 to 24 Months
PRELIMINARY SCHEDULE
FOR PHASE 1a
Roadway Design: Ongoing; Complete Summer 2023
Geotechnical Investigation: Begin Early 2022
Land Acquisition: Begin Fall 2022
Construction: Fall 2023
Anticipated Construction Duration: 12 Months